safety come first for structure installation, operation should be carried out by the trained and professional people with professional skill for the build step.
1.Pull all required permits before starting installation, equipment with hidden danger not allowed to use.
2 .Site ,framing and systems all require inspections
3 .When truss length over 6m, base support ( stabilizer and outrigger should be kept),When connect the truss, the screw/pin must be tight.
5.When the truss system move up and down, people is not allowed to stand below.
6.The high place operation ,please wear safe belt and helmets, shoes should be kept clean, it is forbidden to wear hard bottom shoes
7.Before hoists connect with the cables, must disconnect the power supply first, must unplug the power.
8.In the situation of fog, rain, snow and strong winds weather (when wind speech7.7m/s) , may not be operating on the truss. After Rain and snow operations, anti-skid measures must be taken. After raining weather ,drying maintain must be done
9.Before the lifting of the truss,tools and debris on truss must be removed, to avoid drop wounding movements.
10.Stage installation, marked in accordance with the drawings to install, pay attention to the stage pole not upside down, and from left to right points.
11. Stage Installation, take the order from the front to back, should take the direction of one side. not to build it up from left and right sides together to the middle,
12.Irregular side frame and irregular pole, we all mark the digital on it, please find accordingly goods to build in accordance with the drawings indicated on the goods digital.
13.Screw should be tight when Build the stairs, advoing steps fall down and hurt your legs .
14.Truss and stage, In the transport, storage process is strictly prohibited heavy fall, hit; when in disassembly, prohibited from high-altitude throwing. disassemble In order from top to bottom operation
15.Work is important ,safety life much more important ,keep the tips in mind!
Contact: Lisa
Phone: +86-139-2506-1556
Tel: +86-139-2506-1556
Email: lisa@progrouptruss.com
Add: Dongtai industry Zone,Shiji Town ,Panyu District ,Guangzhou,China